Revive 65 (Mostly finished)
A project to rehabilitate and widen I-65 from the Ohio River to Sellersburg, and to improve interchanges along the way. Most of the project is done; final inspections are expected to finish in June.
Shawnee Expressway Project (Finished)
A complete rehabilitation of the section of I-264 from Dixie Highway west to I-64. This project was finished on time in August 2004.
Ohio River Bridges Project (Approved by FHWA)
A project to build a new bridge across the Ohio River linking I-265 in Indiana to the Gene Snyder Freeway, and a new bridge next to the JFK Bridge to increase I-65's capacity. This project also includes a rebuilding of the Spaghetti Junction south of its current location.
National Turnpike (Under way)
Widening from 2 lanes to 5 between Southside Drive and Outer Loop.
New Cut Road (Completed.)
Widening from 2 lanes to 5 between Southside Drive and the Snyder. Completed.
Crittenden Drive (Completed)
New alignment from south of the Watterson to Grade Lane near Fern Valley Road.
A map of this project is available.
Hurstbourne Parkway (Now Open)
Extension from Bardstown Road to Fern Valley Road.
A map of this project is available.
Jefferson Boulevard (Now open)
1.5-mile extension from McCawley Road (near Jefferson Mall) to Poplar Level Road.
A map of this project is available.
Westport Road (right-of-way)
Widening of two-lane section to five lanes from Hurstbourne Parkway to Hubbards Lane, and new interchange with the Watterson. Right-of-way acquisition nearly complete; scheduled completion fall 2006.
Second Street (Now open to two-way traffic.)
Widening and converstion to two-way between Jefferson and Braodway.
9th and Oak Interchange (Now open.)
A project to build a diamond interchange at the new 9th Street overpass at Oak Street.
Clark Memorial Bridge (Finished)
Rebuilding of entire concrete deck, and fixing of some steel beams.
Court Avenue in Jeffersonville (Completed)
Extension of Court Avenue in Jeffersonville to Missouri Avenue, including signalized intersection with US 31 at the north end of the Second Street Bridge.
10th Street in Jeffersonville (Under way)
Widening of 10th Street in Jeffersonville to five lanes from Spring Street to Pratt Street, expected to be completed by late November; widening from 4 to 5 lanes from Pratt Street to Reeds Lane may not be done until 2004.
Veterans Parkway in Clarksville/Jeffersonville (Complete.)
Along with the Revive 65 Project, a new road connecting Jeffersonville to Clarksville, between Highway 131 and I-265. Clarksville and Jeffersonville sections now open.
A map of this project is available.
Lewis and Clark Parkway in Clarksville
Rebuilding the Lewis and Clark Parkway to include sidewalks and curbs, a widening to six lanes from Eastern Blvd. to I-65, left-turn lane improvements, beautification work, and improvements to some nearby roads. Expected completion in 2005.